How Do I Connect Solar to the Grid in Edmonton?
Your distribution utility in Edmonton is EPCOR, and it sets the connection steps and the rules for credit on exports. Start with its page before you sign a contract or finalise a design.
City permits first
Get City of Edmonton permits, including an electrical permit, before you apply to EPCOR.Interconnection agreement
EPCOR says to expect your interconnection agreement within 14 days of a complete application. Show the signed agreement to the City inspector.Tell your retailer
Your retailer receives micro-generation meter readings and credits exports, so confirm your micro-generation status with it.Larger systems
Projects of 20 kW or more, or any micro-generation system on the network, should email EPCOR before design begins.