How Do I Connect Solar to the Grid in Lethbridge?
Your distribution utility in Lethbridge is City of Lethbridge Electric, and it sets the connection steps and the rules for credit on exports. Start with its page before you sign a contract or finalise a design.
The City is your utility
Lethbridge Electric is the City's own utility, so you apply to the City for an interconnection agreement.Yearly output limit
A system may produce no more than the site's yearly consumption, and must be under 5 MW. Each site's maximum is listed in the City's open data.Permits
An electrical permit is required, and rooftop or wall-mounted panels also need a building permit.Export credits
The page doesn't set out the credit rate. Ask Electric Design at [email protected].